Entered in the project,not verified.
Transformer sizing
Load list → required kVA → recommended standard rating (R10), with current and reactive compensation.
Three sources,three clear labels
Taken from the selected table and its conditions of use,not user input.
A calculated quantity;it must be tied to an input version;A value that has not been calculated must not be shown as 0.
Transformer selection · capacity step
Enter the load list (kW / qty / demand factor / power factor) to get the required kVA and the recommended standard rating. Missing factors show — instead of being filled in for you.
Reactive compensation:
| Load | kW | Qty | Demand factor Kx | cosφ |
|---|---|---|---|---|
Compute capacity & rating
Missing inputs (not substituted)
Recommended:
| Load | Calculated capacity: | Rating rule: | Status |
|---|---|---|---|
| Recommended: | — | Basis: demand factor × coincidence × power factor → calculated capacity → next standard rating up in the R10 series (GB/T 1094.1 / IEC 60076-1). Typical values are shown for reference only and never enter the calculation. | Missing inputs (not substituted) |
| Current: | — | Basis: demand factor × coincidence × power factor → calculated capacity → next standard rating up in the R10 series (GB/T 1094.1 / IEC 60076-1). Typical values are shown for reference only and never enter the calculation. | Missing inputs (not substituted) |
| Margin: | — | Basis: demand factor × coincidence × power factor → calculated capacity → next standard rating up in the R10 series (GB/T 1094.1 / IEC 60076-1). Typical values are shown for reference only and never enter the calculation. | Missing inputs (not substituted) |
Missing inputs (not substituted)
Calculation complete ≠ everything passed
A single item result does not establish that the line or the distribution system can go straight to construction.Site conditions, protection coordination, equipment data and the applicable standard must be verified.
Frequently asked questions
- What can this calculator do?
- Enter a load list — the power of each load in kW, how many of them there are, the demand factor and the power factor — and the calculator sums the demand-referred load, converts it into the apparent power the transformer has to carry and returns the required capacity in kVA, the next standard rating in the R10 series (GB/T 1094.1 / IEC 60076-1), the LV current at that rating and the reactive compensation needed to reach the target power factor. Typical uses: sizing a distribution transformer for a plant extension, checking whether an existing transformer can take an added load, and producing the kVA figure that goes into the purchase specification. A factor you leave out is shown as missing, never silently substituted.
- Which basis and standard series are used for the rating?
- The demand-referred kVA is computed from your load list, and the recommendation is the next rating in the R10 series (GB/T 1094.1 / IEC 60076-1) — a standard step, not an arbitrary number. The LV current follows from that rating and the voltage level, and the reactive compensation from the power factor before and after compensation.
- How does the demand factor change the result?
- The demand factor scales each load before the sum, so it sets the computed kVA directly: a plant with many small loads and low diversity factors needs far less transformer capacity than the arithmetic sum of the nameplate powers suggests. Because the recommendation is the next standard R10 step, a small change in the computed kVA can move the result by one whole step — which is exactly the margin to watch when loads are added later.